  REFINERIES PLANT SPACING CHART        
    Select required Equipment from Dropdown NOTES IN ()  
  FROM   TO DISTANCE  
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
  NOTES   6 NON HAZ. 7.6M HAZ.15M    
  1 STUDY SHOULD BE COMPLETED FOR LOCATIONS   7 CONTROLS INSTALLED NEXT TO OR INSIDE    
  2 SMALL OPEN FLAMES >30M HAZ. AREA   8 STACK <23M HIGH 92M, >23M HIGH 61M    
  3 FROM BATTERY LIMITS   9 TANKS <1590M3 .5DIA SPACING, <7950M3 1DIA, >795M3 1.5DIA    
  4 TANKS >1590m3 76M <1590 46M   10 SERVICE BUILDINGS INCLUDES ALL MISC NON HAZ. BUILDINGS    
  5 TANKS >795m3 61M < 795 30M   11 PROPANE TANKS/SPHERES SHOULD BE MORE REMOTE AND NOT POINT IN THE DIRECTION OF PROCESS PLANTS    